24.04.2019
As part of the technical re-equipment program, a new melting unit, consisting of two melting furnaces with a capacity of 0.4 and 3 tons, is being installed at the Sasovsky Foundry.
Construction and installation work has been ongoing since February 2019. At the moment, construction work has been fully completed, and the installation of technological equipment that is part of the melting plant has been completed. After the commissioning of a new melting unit, it will be possible to produce castings with a larger mass.